L.1 Minor changes and budget flexibility

Minor changes are adjustments that do not have a significant impact on project implementation. Projects can inform the MA/JS about the minor changes, e.g. via progress reports. These changes do not require prior approval by the MA/JS. Table 19 Minor changes in the...

L.0 Changes in the project

During implementation projects might meet challenges that require adjustments in the project set-up. The chapter below summarises the changes that can be introduced into the projects. Types of changes The MA/JS has divided changes into minor and major changes...

K.3 Further rules applicable for all partners

The rules described in the subchapters below are applicable to all partners participating in project implementation (regardless of location and legal status). K.3.1 “Bid-at-three” rule The ‘bid-at-three’ procedure applies when purchasing goods or services with a value...

J.3 Activities not requiring prior approval of MA/JS

Activities outside the Programme area but within the European Union and Norway do not require the prior approval of the MA/JS. In addition, projects implemented under strategy governance do not require prior approval for activities in Iceland. Please note. Project...

J.2 Activities requiring prior approval of MA/JS

If the project intends to implement activities outside the Programme area and/or European Union, the lead partner has to provide the MA/JS with a separate description of the planned activities via BAMOS+, before the activity takes place. Based on the description...

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.