Major changes are more complex adjustments that can have an impact (negative or positive) on the planned outputs and/or solutions, the partnership or the project budget. The list of major changes is described in the table below. Lead partners should follow the below...
Friday, December 10, 2021
Minor changes are adjustments that do not have a significant impact on project implementation. Projects can inform the MA/JS about the minor changes, e.g. via progress reports. These changes do not require prior approval by the MA/JS. Table 19 Minor changes in the...
Friday, December 10, 2021
During implementation projects might meet challenges that require adjustments in the project set-up. The chapter below summarises the changes that can be introduced into the projects. Types of changes The MA/JS has divided changes into minor and major changes...
Friday, December 10, 2021
The rules described in the subchapters below are applicable to all partners participating in project implementation (regardless of location and legal status). K.3.1 “Bid-at-three” rule The ‘bid-at-three’ procedure applies when purchasing goods or services with a value...
Friday, December 10, 2021
Activities outside the Programme area but within the European Union and Norway do not require the prior approval of the MA/JS. In addition, projects implemented under strategy governance do not require prior approval for activities in Iceland. Please note. Project...